Stephen DeAngelis
Most of the world continues to embrace the transition from carbon-based energy generation to green energy generation (e.g., solar and wind). However, futurist Mark van Rijmenam insists there is a problem. He writes, “The world has learned to build clean-energy hardware faster than it can plug it in.”[1] He adds, “In the largest market on earth, finished batteries sit in warehouses, waiting on a grid connection and a transformer that is back-ordered. Set the factory news beside the grid news and one shift comes into view. The scarce thing in the energy transition is no longer the cell. It is the connection.” Supply chain challenges in the green energy sector have been building for some time. Last year, the staff at the International Energy Agency (IEA) noted, “Efforts to expand and modernize electricity transmission grids around the world face mounting challenges as supply chain bottlenecks intensify, according to our new report — which finds that prices and procurement times for essential components like power transformers and cables have almost doubled in four years.”[2] AI and data center growth, as well as the need for backup power, will create long-term exponential demand which means quickly addressing these shortfalls is essential. As energy journalist Rod Walton observes, “The only thing slowing down this acceleration might be the supply chain to feed it. … The overall challenge is critically real and immediate.”[3]
Bottlenecks Short-circuiting the Green Energy Supply Chain
Bottlenecks in the green energy supply chain begin with sourcing essential minerals used in many of the products involved in the green energy sector. Mines simply can’t keep up with demand. Minerals like lithium, cobalt, nickel, and graphite are especially critical for the sector. The staff at Redwood Materials explains, “Certain metals are only found in specific geological formations or regions due to natural geological processes. For example, lithium is primarily extracted from salt flats (brine deposits) in countries like Chile, Argentina, and Bolivia, while cobalt is often mined as a byproduct of copper or nickel mining, with significant deposits in the Democratic Republic of the Congo.”[4] Even if new sources of essential minerals are identified, the problem will persist for years. Journalist Anthony Lopopolo explains, “Fifteen years ago, a mine took an average of 12.7 years from discovery to first production. ... Today the average is 17.9 years. Exploration, feasibility studies, financing, and permitting eat up most of the timeline, and a single permit can outlast multiple political administrations. No new mine can respond to a demand surge in real time.”[5]
Processing of those minerals is also a challenge. Lopopolo reports, “China controls almost all of the refining, processing 65% to 74% of the world's lithium, about 76% of its cobalt, and 94% of its battery-grade graphite, according to the IEA. The countries that mine these minerals don't refine them. Australia, which produces more than half the world's lithium, ships its ore to China, as the Democratic Republic of the Congo does with most of the world's cobalt and Indonesia with more than half of its nickel.”
Transformers are another bottleneck short-circuiting the green energy supply chain. Kevin Shang, Procurement Manager at Masdar (Abu Dhabi Future Energy Company), explains, “The limited supply of transformers has become the new bottleneck of the energy storage supply chain.”[6] In the United States, over 80% of its large power transformers (LPTs) are imported. And the problem could get worse. Jake Hertz, President of NanoHertz Communications, reports, “The estimated average age of an installed LPT in the U.S. is 40 — the end of their operational lifetime.”[7] More recently, the staff at Northfield Transformers reported, “A report by the U.S. Department of Energy highlighted that transformer lead times have reached unprecedented levels, with some large power transformers now requiring over 200 weeks (nearly four years) for delivery. This prolonged wait time threatens critical infrastructure projects, delaying grid expansions and increasing overall costs. Additionally, the National Association of Regulatory Utility Commissioners (NARUC) has warned that supply chain bottlenecks could result in higher energy costs for consumers due to the lack of timely infrastructure upgrades.”[8]
Morgan Bazilian, a Public Policy professor at the Colorado School of Mines, and Kyri Baker, a professor at the University of Colorado Boulder, observe, “Transformers are not the only grid machinery facing delays. A Duke University Nicholas Institute study, citing data from research and consulting firm Wood Mackenzie, shows that high-voltage circuit-breaker lead times reached about 151 weeks — nearly three years — by late 2023, roughly double pre-pandemic norms. Facing similar delays are a range of equipment types, such as transmission cables that can handle high voltages, switchgear — a technical category that includes switches, circuit breakers and fuses — and insulators to keep electricity from going where it would be dangerous. .... High-voltage direct-current cables now take more than 24 months to procure, and offshore wind projects are particularly strained: Orders for undersea cables can take more than a decade to fill. And fewer than 50 cable-laying vessels operate worldwide, limiting how quickly manufacturers can install them, even once they are manufactured.”[9]
Concluding Thoughts
The bottlenecks affecting the green energy supply chain are predicted to last well into the 2030s. There are no quick fixes. There is a growing recognition that battery recycling will help ease the shortage of essential minerals. However, Lopopolo reports, “Recyclers can only process batteries that have died. Most of the batteries installed over the past decade are still working. The IEA estimates that offcuts and rejects from battery factories will remain the main source of recyclable material until after 2035. For the rest of this decade, there's no third source of minerals. Even when dead batteries finally start arriving in volume after 2030, recycling won't solve most of the problem. Recycled metals would meet only 20% to 30% of demand for lithium, nickel, and cobalt by 2050.”
Downstream in the green energy supply chain, bottlenecks will also continue until production is increased. Van Rijmenam observes, “For a decade the fight was to make the machines cheap enough. That fight is over, and it is won. The factory has become the easy part. The hard part is the wire.” He explains that components connecting energy generation to grids is “the slow part, the part on back-order.” He adds, “Manufactured clean power that cannot reach the grid is stranded capital, not progress.” Part of the solution, he asserts, is to eliminate as much of grid as possible. “Build the factory next to the demand and the port, the way the Suez plant does. Invest in the transformers, the switchgear, and the flexibility software that move power without new lines. … The builders who scale the connection will run the decade [while] the rest spend waiting in the queue.”
Footnotes
[1] Mark van Rijmenam, “The Battery Is Solved. The Grid Connection Is the Wall,” Synthetic Minds Newsletter, 21 August 2026.
[2] Staff, “The supply chain challenges facing the world's electricity grids,” International Energy Agency, 11 March 2025.
[3] Rod Walton, “The Rise of Battery Storage, Constraints in Supply Chain and a Holistic Path Forward: Jacobs Perspective,” EnergyTech, 21 September 2026.
[4] Staff, “Understanding the battery supply chain and the role of critical minerals,” Redwood Materials.
[5] Anthony Lopopolo, “The world's battery boom depends on a supply chain that could snap at any time,” Quartz, 21 August 2026.
[6] Marija Maisch, “Transformer shortages: New bottleneck of the energy storage supply chain,” PV Magazine, 1 November 2023.
[7] Jake Hertz, “Addressing Transformer Supply Chain Challenges for a Resilient Grid,” EE Power, 25 August 2023.
[8] Staff, “Navigating Challenges in the Transformer Supply Chain in 2025 and Beyond,” Northfield Transformers Blog, 30 January 2025.
[9] Morgan Bazilian and Kyri Baker, “Supply chain delays, rising prices threaten electricity grid,” Finance & Commerce, 24 November 2025.